Short answer

Almost always, yes. Baltimore County requires a building permit for accessory structures over 120 square feet, Howard County requires one for sheds and barns over 200 square feet, and Anne Arundel County lists garages as “permit required.” Zoning then decides where the garage sits and how tall it can be. In Baltimore County, that means the rear yard, at least 2.5 feet from side and rear lot lines and no more than 15 feet tall.

A detached garage sits on footings, adds lot coverage and usually ends up closer to a neighbor than the house. So each county reviews it twice: for zoning (where it goes and how big it is) and for the building code (how it is built).

This guide is about building a new detached garage or a larger accessory building. Turning an existing garage into a bedroom or office follows different rules, covered in our garage conversion guide for Maryland homeowners.

Start with your county

Garage permits and zoning in this area are handled by the county, so first confirm which government your property is in. A Baltimore mailing address does not always mean Baltimore City: Catonsville, Towson and Pikesville are in Baltimore County.

Baltimore City is separate. Its Department of Housing and Community Development publishes the city’s permit rules and applications go through E-Permits, so the county numbers below do not apply there.

County comparison at a glance

CountyWhen a permit is neededPlacement and height rules
Baltimore CountyAccessory structures over 120 sq ft, and any size in a historic district, the floodplain, the Chesapeake Bay Critical Area or on a Landmarks List propertyRear yard behind the rear foundation wall line; 2.5 ft from side and rear lot lines; 15 ft maximum height; no more than 40% of the yard
Howard CountyThe permit office’s FAQ says sheds and barns over 200 sq ft need a building permitSetbacks and height set by zoning district; all accessory structures combined capped at 600 sq ft on lots in the planned public water and sewer area
Anne Arundel CountyGarages are listed as “permit required”; a garage within 3 ft of the house counts as attachedR5 district example: 40 ft front, 7 ft side and rear, 15 ft corner side; height of 25 ft or the house height, whichever is less
An easement, a plat setback, a floodplain or the Critical Area can change these answers for your lot, so confirm with the county for your address.

Baltimore County

Baltimore County’s Department of Permits, Approvals and Inspections (PAI) treats garages, sheds and gazebos as accessory structures, with the permit triggers shown in the table above. Its building guidelines:

  • Location: rear yard, behind the rear foundation wall line, unless you get a zoning variance. On a corner lot, the half of the lot farthest from the side street.
  • Setbacks: 2.5 feet from side and rear property lines. Any side closer than 5 feet needs a one-hour fire-rated wall with no openings. With an alley, 15 feet from the alley centerline.
  • Size and height: no more than 40 percent of the yard and no taller than 15 feet.
  • Footings: frost-line footings for structures over 400 square feet. In a 100-year floodplain, the structure must be anchored and vented.

The county also states that an MHIC licensed contractor must be used, and all building permit applications are filed online.

Howard County

Howard County splits the job. The Department of Inspections, Licenses and Permits (DILP) issues the building permit, and the Department of Planning and Zoning (DPZ) controls setbacks, height and size.

DILP’s FAQ says building permits are required for sheds over 200 square feet and for barns over 200 square feet in residential zoning areas, and that sheds and barns over 400 square feet need frost footings at least 30 inches below grade. A garage built to hold a car will usually be past the 200 square foot line, so plan on a permit.

DPZ’s FAQ says a garage or accessory building cannot be larger than the house. It also caps the combined footprint of all accessory structures on a lot with a single-family detached home: 600 square feet in the planned public water and sewer service area, with larger allowances on rural RC and RR lots. An existing shed counts toward that total.

There is no countywide garage setback. Detached structures follow the accessory structure setbacks for your zoning district, and DILP refers placement questions to DPZ. Where a setback will not work, you can request an administrative adjustment or a variance.

Anne Arundel County

Anne Arundel County’s “Do I Need a Permit?” page lists garages as permit required. A garage within 3 feet of the house is treated as attached; one farther away is a detached accessory structure. In the R5 residential district, for example, the county code sets these minimums for accessory structures other than sheds of 64 square feet or less and 8 feet or less in height:

R5 accessory structure ruleRequirement
Front lot line40 ft
Side and rear lot lines7 ft (5 ft for structures under 8 ft tall)
Corner side lot line15 ft
Maximum height25 ft or the height of the house, whichever is less

Other districts use different numbers. Near the water, the county’s Critical Area covers land within 1,000 feet of mean high tide or the edge of tidal wetlands, and accessory structures and driveways count toward its lot coverage limits. Inside the 100-foot Critical Area Buffer, the county says a variance is generally required before any disturbance.

Brick and board-and-batten home exterior with new front porch and gables remodeled by Wall to Wall Construction, with a before photo inset
Exterior projects that change a home’s footprint go through both zoning and building review.

Zoning review vs. building permit

ZoningWhere the garage goes, distance from lot lines, height and lot coverage. If a spot fails, the remedy is a variance or a new location.
Building permitHow it is built: footings, framing, roof and fire-rated walls near lot lines, checked on drawings and by inspectors.
Other reviewsFloodplain, Critical Area, historic district, well and septic, and grading, depending on the lot.

Settle zoning first, then pay for construction drawings.

What to submit and how long review takes

Baltimore County asks for an Accessory Structure Letter with a handwritten signature and a site plan with every application, plus construction plans for structures of 1,000 square feet and over. On well and septic, the site plan must meet the county’s Ground Water Site Plan Requirements.

Anne Arundel County asks for a building permit application, construction plans drawn to an architectural scale showing dimensions, materials and construction methods, and a site plan drawn to an engineering scale showing easements, property lines, rights of way and any grinder pump, well or septic system. The fee is based on the estimated value of the work.

Howard County applications go through DILP’s online Citizens Access Portal. Ask DILP for its current checklist before drawings start.

None of the three counties publishes a fixed turnaround for garage permits. In Baltimore County, the application goes to every reviewing department after fees are paid, and comments can require revised drawings. A complete submission avoids extra rounds; ask the permit office for current timing.

HOAs, wells and power

  • HOA or covenants. A county permit does not replace your community’s architectural approval. Get that sign-off first.
  • Electrical and plumbing. Baltimore County processes electrical and plumbing permits separately from building permits, and Howard County inspects them separately.
  • Well and septic. In Baltimore County, if new space could add a bedroom or increase occupancy on a well and septic property, you must show the system is adequate.

If you are weighing a garage against adding space to the house, our home additions team can price both, including in Catonsville, Ellicott City and Severn.

Key takeaways

  • Plan on a permit for a detached garage in Baltimore, Howard or Anne Arundel County.
  • Baltimore County: rear yard, 2.5 ft from side and rear lines, 15 ft maximum height.
  • Howard County: setbacks by zoning district and a 600 sq ft combined cap on lots in the public water and sewer area.
  • Anne Arundel County R5: 7 ft side and rear setbacks, 25 ft or the house height, whichever is less.

Frequently asked questions

Do I need a permit for a detached garage in Maryland?
Almost always. Baltimore County requires a permit for accessory structures over 120 square feet, Howard County for sheds and barns over 200 square feet, and Anne Arundel County lists garages as permit required.
How close to the property line can I build a detached garage?
Baltimore County allows 2.5 feet from side and rear lot lines, with a fire-rated wall on any side closer than 5 feet. Anne Arundel County’s R5 district requires 7 feet. Howard County sets setbacks by zoning district.
How big can a detached garage be in Howard County?
No larger than the house. On a lot in the planned public water and sewer service area, all accessory structures combined are limited to 600 square feet.
Can I build a small shed without a permit?
Sometimes. Anne Arundel County exempts sheds 150 square feet or less and no more than 10 feet tall, except in the Critical Area. Baltimore County’s line is 120 square feet, but any size needs a permit in a historic district, the floodplain or the Critical Area. Howard County’s line is 200 square feet.

Planning a garage or accessory building?

Wall to Wall Construction has been a design-build remodeler since 2005. We check your lot against the county rules, prepare the drawings and file the permit, then give you a clear, itemized estimate. MHIC #123700.

Wall to Wall Construction, LLC · 11 Newburg Ave, Ste 100, Catonsville, MD 21228 · 410-788-3990 · MHIC #123700 · MHBR #6236
Call Request A Quote